Palm Bay Yacht Club

40-Year Recertification Project

​

780 NE 69th St, Miami, FL 33138

Last Updated: November 11, 2026
Action Required

All lines: Keep balcony doors and windows closed during active repair work and follow posted safety notices.

Critical

06 & 08 Lines: Balcony doors are secured for safety. Do not open them, access balconies or remove posted signs.

What You Need To Do

  • 01 LineEarly / nowClear furniture, window coverings and personal items from windows and balconies early. Crews may reach your unit ahead of schedule. Ask the front desk or project team if you need assistance.
  • 02 LineNowBook your unit punch-out appointment if you have not already done so.
  • 10 Line12/14/2026Clear furniture, window coverings and personal items from the window and balcony work areas.
  • 04 Line12/28/2026Clear furniture, window coverings and personal items from the window and balcony work areas.
  • 06 & 08 Lines04/05/2027Arrange clearance of furniture, window coverings and personal items with the project team. Do not enter a locked-out balcony.

Find Your Line

Select your unit's line to see its schedule.

Line 01

In Progress

Latest reported: Kitchen and balcony window installation continues. Bedroom concrete work awaits inspection approval. Phase 2 balcony windows target December 1; the full balcony window scope targets April 8, 2027.

Action (Early / now): Clear furniture, window coverings and personal items from windows and balconies early. Crews may reach your unit ahead of schedule. Ask the front desk or project team if you need assistance.

Kitchen side of building (outside)

Next up

Windows & doors

12/28/2026

Est. finish

02/16/2027

  1. Crews arriveCompleted
  2. Windows & doors12/28/2026
  3. Sealing & painting01/26/2027
  4. Final finishes02/15/2027
  5. Crews leave02/16/2027

Bedroom side of building (outside)

Next up

Windows & doors

03/16/2027

Est. finish

05/05/2027

  1. Crews arriveCompleted
  2. Windows & doors03/16/2027
  3. Sealing & painting04/14/2027
  4. Final finishes05/04/2027
  5. Crews leave05/05/2027

Balcony side of building

Next up

Windows & doors

04/08/2027

Est. finish

08/19/2027

  1. Crews arriveCompleted
  2. Concrete repairCompleted
  3. Windows & doors04/08/2027
  4. Sealing & painting07/01/2027
  5. Railings07/29/2027
  6. Final finishes08/18/2027
  7. Crews leave08/19/2027

Schedule history

  • Balcony: 08/23/2027 → 08/19/2027 (changed 11/11/2026)Why: Tracking ahead of schedule.

Dates are stage completion targets, except “Crews arrive,” which is a start date. “Crews leave” is the scheduled end of that exterior scope, not final city sign-off. Dates may shift with weather, added repairs or unit access.

What Changed in the Schedule

Finish dates that moved in the 11/11/2026 update: the old date, the new date, and why.

Latest tower finish

08/10/202808/28/202818 days later

  • 01 Line · Balcony

    Ahead

    Was 08/23/2027Now 08/19/2027−4 days earlier

    Why: Tracking ahead of schedule.

  • 02 Line · Balcony

    Delayed

    Was 11/26/2026Now 01/26/2027+61 days later

    Why: Rain and high-wind days, plus additional work found in the field.

  • 03/05 Line · Balcony

    Delayed

    Was 10/12/2027Now 12/28/2027+77 days later

    Why: Additional railing-related work.

  • 04 Line · Balcony

    Delayed

    Was 03/02/2028Now 04/27/2028+56 days later

    Why: Reason pending from management

  • 07 Line · Balcony

    Delayed

    Was 12/29/2027Now 04/19/2028+112 days later

    Why: Reason pending from management

  • 09 Line · Balcony

    Delayed

    Was 11/24/2027Now 05/12/2028+170 days later

    Why: Reason pending from management

  • 10 Line · Balcony

    Delayed

    Was 04/24/2028Now 06/12/2028+49 days later

    Why: Reason pending from management

  • 06 Line · Balcony

    Delayed

    Was 08/10/2028Now 08/28/2028+18 days later

    Why: Reason pending from management

  • 08 Line · Balcony

    Delayed

    Was 08/10/2028Now 08/28/2028+18 days later

    Why: Reason pending from management

Latest Update

Resident Bulletin No. 4

10/26/2026 – 11/06/2026
  • 02 Line balcony finish has moved from November 26, 2026 to January 26, 2027 because of weather and additional work.
  • 01 Line is tracking ahead of schedule. Residents should clear window and balcony obstructions early.
  • Concrete repairs continue on Lines 03, 05, 07 and 09; excavation continues on Lines 04 and 10.
  • 06 and 08 Lines: balcony lockout and railing and flooring removal continue.
  • Pool permit drawings are under Florida Department of Health review; amenity deck drawings are being finalized.
  • Next resident bulletin: November 25, 2026.

Next Two Weeks

Published look-ahead: 11/11–11/21. Work may pause for rain or wind.

  • 11/11

    • X01 · Kitchen & Bedroom side – Window installation (Phase 4)
    • X01 · Balcony – Window installation (Phase 2 of 4)
    • X01 · Balcony – Repairs after window installation, Units 1701–1801
    • X01 · Balcony – Weather walls, management office to Unit 501
    • X02 · Balcony – Ceiling and center column painting
    • X03/05 · Bedroom side – Window opening concrete repairs (Phase 2 of 4)
    • X03/05 · Balcony – Concrete repairs (Phase 2 of 4)
    • X04 · Balcony – Excavation and marking
    • X06/08 · Balcony – Railing and flooring removal and lockout
    • X07 · Balcony – Slab concrete repairs (Phase 1 of 2)
    • X09 · Balcony – Slab concrete repairs
    • X10 · Balcony – Excavation and marking
  • 11/12

    • X01 · Kitchen & Bedroom side – Window installation (Phase 4)
    • X01 · Balcony – Window installation (Phase 2 of 4)
    • X01 · Balcony – Repairs after window installation, Units 1701–1801
    • X01 · Balcony – Weather walls, management office to Unit 501
    • X02 · Balcony – Ceiling and center column painting
    • X03/05 · Bedroom side – Window opening concrete repairs (Phase 2 of 4)
    • X03/05 · Balcony – Concrete repairs (Phase 2 of 4)
    • X04 · Balcony – Excavation and marking
    • X06/08 · Balcony – Railing and flooring removal and lockout
    • X07 · Balcony – Slab concrete repairs (Phase 1 of 2)
    • X09 · Balcony – Slab concrete repairs
    • X10 · Balcony – Excavation and marking
  • 11/13

    • X01 · Kitchen & Bedroom side – Window installation (Phase 4)
    • X01 · Balcony – Window installation (Phase 2 of 4)
    • X01 · Balcony – Repairs after window installation, Units 1701–1801
    • X01 · Balcony – Weather walls, management office to Unit 501
    • X02 · Balcony – Ceiling and center column painting
    • X03/05 · Bedroom side – Window opening concrete repairs (Phase 2 of 4)
    • X03/05 · Balcony – Concrete repairs (Phase 2 of 4)
    • X04 · Balcony – Excavation and marking
    • X06/08 · Balcony – Railing and flooring removal and lockout
    • X07 · Balcony – Slab concrete repairs (Phase 1 of 2)
    • X09 · Balcony – Slab concrete repairs
    • X10 · Balcony – Excavation and marking
  • 11/14

    • X*01 · Kitchen & Bedroom side – Window installation (Phase 4)
    • X*01 · Balcony – Window installation (Phase 2 of 4)
    • X*01 · Balcony – Repairs after window installation, Units 1701–1801
    • X*01 · Balcony – Weather walls, management office to Unit 501
    • X*02 · Balcony – Ceiling and center column painting
    • X*03/05 · Bedroom side – Window opening concrete repairs (Phase 2 of 4)
    • X*03/05 · Balcony – Concrete repairs (Phase 2 of 4)
    • X*04 · Balcony – Excavation and marking
    • X*06/08 · Balcony – Railing and flooring removal and lockout
    • X*07 · Balcony – Slab concrete repairs (Phase 1 of 2)
    • X*09 · Balcony – Slab concrete repairs
    • X*10 · Balcony – Excavation and marking
LineWork11/1111/1211/1311/1411/1611/1711/1811/1911/2011/21Status / Target
01Kitchen & Bedroom side – Window installation (Phase 4)XXXX*XXXXXX*In Progress
01Balcony – Window installation (Phase 2 of 4)XXXX*XXXXXX*In Progress
01Balcony – Repairs after window installation, Units 1701–1801XXXX*XXXXXX*In Progress
01Balcony – Weather walls, management office to Unit 501XXXX*XXXXXX*In Progress
02Balcony – Ceiling and center column paintingXXXX*XXXXXX*In Progress
03/05Bedroom side – Window opening concrete repairs (Phase 2 of 4)XXXX*XXXXXX*In Progress
03/05Balcony – Concrete repairs (Phase 2 of 4)XXXX*XXXXXX*In Progress
04Balcony – Excavation and markingXXXX*XXXXXX*In Progress
06/08Balcony – Railing and flooring removal and lockoutXXXX*XXXXXX*In Progress
07Balcony – Slab concrete repairs (Phase 1 of 2)XXXX*XXXXXX*In Progress
09Balcony – Slab concrete repairsXXXX*XXXXXX*In Progress
10Balcony – Excavation and markingXXXX*XXXXXX*In Progress
X ScheduledX* Only if needed (weather permitting)FH Federal holidayPD Partial day (weather)

Project Timeline

Started: Jul 2024(approx.)Latest scheduled tower finish: Aug 2028

About 1 yr 9 mo to go · 57% of the planned time has passed

Show dates for:

  • Crews arrive

    Under way – Feb 2027

    Crew sets up equipment and protection at the line.

    Done on 4 of 10 lines

  • Concrete repair

    Under way – Jul 2027

    Damaged concrete on balconies and walls is removed and rebuilt.

    Done on 2 of 10 lines

  • Windows & doors

    Under way – Mar 2028

    New windows and sliding doors are installed.

    Done on 1 of 10 lines

  • Sealing & painting

    Dec 2026 – Jul 2028

    Exterior surfaces are sealed and painted as one scheduled work stage.

    Done on 0 of 10 lines

  • Railings

    Jan 2027 – Aug 2028

    New balcony railings are installed.

    Done on 0 of 10 lines

  • Final finishes

    Jan 2027 – Aug 2028

    Final exterior finishing work before crews leave the building side.

    Done on 0 of 10 lines

  • Crews leave

    Jan 2027 – Aug 2028

    Equipment is removed and work on the line is finished.

    Done on 0 of 10 lines

  • ◆ Next bulletinNov 2026
  • ◆ 02 Line scope finishJan 2027 (est.)
  • ◆ Latest scheduled tower scope finishAug 2028 (est.)
Time already passed Planned Estimated Key date

Dates are targets and may shift. The latest scheduled tower scope ends August 2028; dates for unscheduled exterior scopes, amenity reopening and final city sign-off are not confirmed.

Progress & Cost

Budget

Original contract— Pending
Approved changes— Pending
Current total— Pending
Paid to date— Pending

Waiting on updated figures from management (last reported 03/20/2026).

Progress & Schedule

Overall progress— Pending
Project start07/01/2024 (approx.)
Original finish— Pending
Latest tower scope finish (est.)08/28/2028
Days delayed— Pending

Items marked "Pending" are waiting on updated figures from management.

Main reasons dates shift

  • Weather
  • Conditions found after demolition
  • Added scope
  • Unit access
  • Pool permit

Pool & Amenity Deck

  • Pool permit

    Pending

    Florida Department of Health has received the drawings and is reviewing them. The next phase of pool work awaits approval.

  • Amenity deck design

    Nearing Approval

    Drawings are being finalized for Board approval; final pricing follows.

  • Garage – lower level

    In Progress

    One floor-work phase is substantially complete; the next phase is underway.

  • Garage – main drain line

    Under Review

    Replacement is planned. Pricing and timing are being finalized.

  • Garage – water intrusion

    Monitoring

    The source of minor water at weep holes during heavy rain is being evaluated.

  • Amenity deck drainage, plumbing & electrical

    In Progress

    Coordination continues with the design team.

  • Gazebo modifications

    In Progress

    Work continues as part of the amenity deck scope.

Living With Construction

Work Hours

Monday–Saturday, 8:30 AM–5:00 PM. Concrete pours may start at 7:00 AM to avoid afternoon rain. Pours are low-noise, but formwork checks may be audible.

Privacy

Workers operate outside units on swing stages. Keep window treatments closed during work hours, except where the team asks you to clear them for access.

Noise & Vibration

Demolition can affect active and adjacent lines. Remove artwork, shelving and breakables from walls facing the work.

Dust

Use painter’s tape around balcony doors and windows; place towels or foam in door tracks.

Parking

Avoid construction no-park zones and areas marked with cones or caution tape.

Loose Items

Secure or remove loose items where safe. Report construction debris to Property Management. Never access a locked-out balcony.

Weather

Rain, lightning, high winds or excessive heat may pause swing stage work even if conditions on the ground seem clear.

Project Contacts

Submit a question or concern

Gustavo Sanin

Owner's Representative — m2e (general project questions)

Sarah Farooque

Project Coordinator — m2e (general project questions)

Jessica Vela

Project Coordinator — C&S (windows & weather walls; on site five days/week)

Brandon Rodriguez

Project Coordinator — C&S (windows & weather walls; on site five days/week)

The project team responds within 48 hours. Urgent concerns receive immediate attention. If you cannot use the form, contact Property Management in Building Management Office 201.

Document Vault

Words You May See

Mobilization
Crews and equipment arrive and set up on your line.
Fenestration
Replacing windows and sliding doors.
Parging
Smoothing repaired concrete before sealing and paint.
Waterproofing
Sealing balconies so water can't get in.
Punch-out
Final walkthrough of your unit to fix small items.
Demobilization
Crews remove equipment and leave your line.