Palm Bay Yacht Club
780 NE 69th St, Miami, FL 33138
All lines: Keep balcony doors and windows closed during active repair work and follow posted safety notices.
06 & 08 Lines: Balcony doors are secured for safety. Do not open them, access balconies or remove posted signs.
Select your unit's line to see its schedule.
Latest reported: Kitchen and balcony window installation continues. Bedroom concrete work awaits inspection approval. Phase 2 balcony windows target December 1; the full balcony window scope targets April 8, 2027.
Next up
Windows & doors
12/28/2026
Est. finish
02/16/2027
Next up
Windows & doors
03/16/2027
Est. finish
05/05/2027
Next up
Windows & doors
04/08/2027
Est. finish
08/19/2027
Schedule history
Dates are stage completion targets, except “Crews arrive,” which is a start date. “Crews leave” is the scheduled end of that exterior scope, not final city sign-off. Dates may shift with weather, added repairs or unit access.
Finish dates that moved in the 11/11/2026 update: the old date, the new date, and why.
Latest tower finish
08/10/202808/28/202818 days later
01 Line · Balcony
AheadWas 08/23/2027Now 08/19/2027−4 days earlier
Why: Tracking ahead of schedule.
02 Line · Balcony
DelayedWas 11/26/2026Now 01/26/2027+61 days later
Why: Rain and high-wind days, plus additional work found in the field.
03/05 Line · Balcony
DelayedWas 10/12/2027Now 12/28/2027+77 days later
Why: Additional railing-related work.
04 Line · Balcony
DelayedWas 03/02/2028Now 04/27/2028+56 days later
Why: Reason pending from management
07 Line · Balcony
DelayedWas 12/29/2027Now 04/19/2028+112 days later
Why: Reason pending from management
09 Line · Balcony
DelayedWas 11/24/2027Now 05/12/2028+170 days later
Why: Reason pending from management
10 Line · Balcony
DelayedWas 04/24/2028Now 06/12/2028+49 days later
Why: Reason pending from management
06 Line · Balcony
DelayedWas 08/10/2028Now 08/28/2028+18 days later
Why: Reason pending from management
08 Line · Balcony
DelayedWas 08/10/2028Now 08/28/2028+18 days later
Why: Reason pending from management
Published look-ahead: 11/11–11/21. Work may pause for rain or wind.
11/11
11/12
11/13
11/14
| Line | Work | 11/11 | 11/12 | 11/13 | 11/14 | 11/16 | 11/17 | 11/18 | 11/19 | 11/20 | 11/21 | Status / Target |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | Kitchen & Bedroom side – Window installation (Phase 4) | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 01 | Balcony – Window installation (Phase 2 of 4) | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 01 | Balcony – Repairs after window installation, Units 1701–1801 | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 01 | Balcony – Weather walls, management office to Unit 501 | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 02 | Balcony – Ceiling and center column painting | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 03/05 | Bedroom side – Window opening concrete repairs (Phase 2 of 4) | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 03/05 | Balcony – Concrete repairs (Phase 2 of 4) | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 04 | Balcony – Excavation and marking | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 06/08 | Balcony – Railing and flooring removal and lockout | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 07 | Balcony – Slab concrete repairs (Phase 1 of 2) | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 09 | Balcony – Slab concrete repairs | X | X | X | X* | X | X | X | X | X | X* | In Progress |
| 10 | Balcony – Excavation and marking | X | X | X | X* | X | X | X | X | X | X* | In Progress |
About 1 yr 9 mo to go · 57% of the planned time has passed
Show dates for:
Crews arrive
Under way – Feb 2027
Crew sets up equipment and protection at the line.
Done on 4 of 10 lines
Concrete repair
Under way – Jul 2027
Damaged concrete on balconies and walls is removed and rebuilt.
Done on 2 of 10 lines
Windows & doors
Under way – Mar 2028
New windows and sliding doors are installed.
Done on 1 of 10 lines
Sealing & painting
Dec 2026 – Jul 2028
Exterior surfaces are sealed and painted as one scheduled work stage.
Done on 0 of 10 lines
Railings
Jan 2027 – Aug 2028
New balcony railings are installed.
Done on 0 of 10 lines
Final finishes
Jan 2027 – Aug 2028
Final exterior finishing work before crews leave the building side.
Done on 0 of 10 lines
Crews leave
Jan 2027 – Aug 2028
Equipment is removed and work on the line is finished.
Done on 0 of 10 lines
Dates are targets and may shift. The latest scheduled tower scope ends August 2028; dates for unscheduled exterior scopes, amenity reopening and final city sign-off are not confirmed.
Waiting on updated figures from management (last reported 03/20/2026).
Items marked "Pending" are waiting on updated figures from management.
Main reasons dates shift
Pool permit
PendingFlorida Department of Health has received the drawings and is reviewing them. The next phase of pool work awaits approval.
Amenity deck design
Nearing ApprovalDrawings are being finalized for Board approval; final pricing follows.
Garage – lower level
In ProgressOne floor-work phase is substantially complete; the next phase is underway.
Garage – main drain line
Under ReviewReplacement is planned. Pricing and timing are being finalized.
Garage – water intrusion
MonitoringThe source of minor water at weep holes during heavy rain is being evaluated.
Amenity deck drainage, plumbing & electrical
In ProgressCoordination continues with the design team.
Gazebo modifications
In ProgressWork continues as part of the amenity deck scope.
Monday–Saturday, 8:30 AM–5:00 PM. Concrete pours may start at 7:00 AM to avoid afternoon rain. Pours are low-noise, but formwork checks may be audible.
Workers operate outside units on swing stages. Keep window treatments closed during work hours, except where the team asks you to clear them for access.
Demolition can affect active and adjacent lines. Remove artwork, shelving and breakables from walls facing the work.
Use painter’s tape around balcony doors and windows; place towels or foam in door tracks.
Avoid construction no-park zones and areas marked with cones or caution tape.
Secure or remove loose items where safe. Report construction debris to Property Management. Never access a locked-out balcony.
Rain, lightning, high winds or excessive heat may pause swing stage work even if conditions on the ground seem clear.
Jessica Vela
Project Coordinator — C&S (windows & weather walls; on site five days/week)
Brandon Rodriguez
Project Coordinator — C&S (windows & weather walls; on site five days/week)
The project team responds within 48 hours. Urgent concerns receive immediate attention. If you cannot use the form, contact Property Management in Building Management Office 201.